Skip to main content

130R-23: Demonstrating Entitlement to Cumulative Impact Claims in Construction [May 15, 2023]

130R-23: Demonstrating Entitlement to Cumulative Impact Claims in Construction
AACE International, May 15, 2023

Price: $0 (Member) / $100 (Non-Member)
1-CLICK DOWNLOAD FOR MEMBERS

This recommended practice (RP) of AACE International provides guidance on the process to demonstrate entitlement to cumulative impact claims on a construction project when a process for addressing cumulative impact claims is not addressed in the contract terms. This process applies across all common construction contracting strategies or delivery methods if the contract terms do not address any or some aspects of the procedure to address cumulative impact claims.

This RP is intended to provide guidelines (i.e., not be a mandated standard) for a suggested process to use when submitting a contract change order request (COR) or claim associated with cumulative impact and what to look for when defending or analyzing such claims on construction projects. This recommended practice represents the concepts most practitioners consider a good industry practice to use and recommend. This recommended practice is relevant to stakeholders on a construction project, whether owner, designer, contractor, subcontractor, construction manager, or others. Although this recommended practice is written in the context of a contract between an owner and prime contractor, it is applicable to any party contracted to perform work on a project, including contracts between prime contractors and their subcontractors and their suppliers.

The concept of cumulative impact has been recognized within the construction industry internationally for many years. It has also been referred to as ripple effect or knock-on effect and as a global claim in English literature and case law. Cumulative impact is defined as the net impact of two or more undifferentiated changes, as each is measured or measurable at a certain point in time, being much greater than the sum of the effect of the individual parts. This effect results in the reduced productivity of unchanged work. Due to the complicated nature of construction work, it is not usually well understood by contracting parties and even legal professionals. Cumulative impact, when it occurs on a construction project, is often referred to as an indirect disruption or loss of productivity claim. There is no specific number or total value of changes on a project that, once reached, create the circumstance for a cumulative impact. The terms of most construction contracts allow for changes, but they do not typically define any maximum limit for changes. This lack of a contractual limit can lead to disputes regarding whether the number or value of changes was reasonable or foreseeable.

This RP provides a basic understanding of cumulative impact and outlines the steps necessary to demonstrate or refute a contractor’s entitlement to the potential damages that may result. Cumulative impact is defined as:
  • The unforeseeable disruption of productivity resulting from the synergistic effect of an undifferentiated group of changes. Cumulative impact is referred to as the ripple effect of changes on unchanged work that causes a decrease in productivity and is not analyzed in terms of spatial or temporal relationships; and
  • The impact on unchanged work, which is not attributable to any one change but flows from the synergy of the number and scope of changes issued on a project.
In a cumulative impact claim, the aggrieved contractor seeks compensation for the collective damage caused by all of the changes in addition to particularizing the damages arising from each change. Cumulative impact claims are often erroneously called total cost claims. Total cost describes a method for quantifying cumulative impact claims not the actual condition per se.

[Look Inside]